⁦Infrastructure profile⁩⁦Active⁩

⁦Parand Power Plant⁩

⁦Parand Power Plant is a natural-gas-fired facility developed from a six-unit⁩, 954 ⁦MW gas plant into a combined-cycle installation⁩. ⁦MAPNA operates the plant⁩, ⁦which had approximately 1⁩,580 ⁦MW reported capacity in 2023 and uses treated municipal wastewater from Parand for its steam units⁩.

⁦Status⁩⁦Active⁩
⁦Verification⁩⁦Basic⁩
⁦Confidence⁩⁦Medium⁩
⁦Updated⁩19/07/2026
⁦Strategic Layer⁩

⁦Strategic and market-access role⁩

⁦Parand Power Plant matters in the Hormuz Graph because it sits on Tehran’s southwestern growth belt⁩, ⁦where residential expansion⁩, ⁦logistics parks⁩, ⁦industrial estates⁩, ⁦rail-linked movement⁩, ⁦and airport-adjacent development create rising electricity demand⁩. ⁦Its role is not only grid generation⁩; ⁦it connects the capital-region power system to Parand⁩, ⁦Robat Karim⁩, ⁦Imam Khomeini Airport logistics⁩, ⁦and Tehran-facing enterprise demand⁩. ⁦The asset is useful for reading how electricity resilience affects warehousing⁩, ⁦commuter settlements⁩, ⁦manufacturing⁩, ⁦and service operations around one of Tehran Province’s most active expansion corridors⁩.

⁦OPERATING PROFILE⁩

⁦Operations⁩, ⁦capacity⁩ &⁦amp⁩; ⁦connectivity⁩

⁦Related use cases⁩

⁦Useful for power-supply risk assessment⁩, ⁦industrial and logistics site screening⁩, ⁦real estate resilience review⁩, ⁦public-project monitoring⁩, ⁦and demand mapping for backup power⁩, ⁦efficiency⁩, ⁦and grid-support services⁩. ⁦Analysts can use it to assess how electricity constraints affect Parand⁩, ⁦airport-linked logistics⁩, ⁦southwestern Tehran warehousing⁩, ⁦and manufacturing operations⁩. ⁦Due diligence should verify current grid role⁩, ⁦fuel exposure⁩, ⁦maintenance condition⁩, ⁦local power shortages⁩, ⁦and procurement pathways⁩.

⁦Capacity and service area⁩

⁦Capacity⁩: ⁦Approximately 1⁩,580 ⁦MW combined-cycle capacity reported by MAPNA in 2023⁩; ⁦Global Energy Monitor reported 1⁩,578 ⁦MW⁩. ⁦MAPNA reported a 90 MW increase from recent projects⁩. ⁦Service area⁩: ⁦Tehran’s southwestern growth belt⁩, ⁦including Parand⁩, ⁦Robat Karim⁩, ⁦Imam Khomeini Airport logistics and nearby industrial and residential developments⁩.

⁦Industries served⁩

⁦Electricity supply for industrial⁩, ⁦logistics⁩, ⁦airport-linked⁩, ⁦residential and commercial demand⁩.

⁦CONTROL⁩ &⁦amp⁩; ⁦DEVELOPMENT⁩

⁦Ownership⁩, ⁦operation⁩ &⁦amp⁩; ⁦expansion⁩

⁦Owner and operator⁩

⁦Owner⁩: ⁦MAPNA Parand Power Generation Co⁩. (100% ⁦reported by Global Energy Monitor⁩, 2023). ⁦Operator⁩: ⁦MAPNA Group⁩

⁦Opening or commissioning⁩

2006 ⁦for the gas section⁩. ⁦Combined-cycle conversion was commissioned in stages⁩, ⁦including units reported in 2018 and 2020⁩.

⁦Expansion and development projects⁩

⁦MAPNA reported conversion of gas units to combined cycle through MAP2B/MAP2C upgrades⁩, ⁦adding 90 MW of capacity⁩. ⁦Steam units use treated wastewater from Parand city⁩; ⁦the associated project was reported with⁩ €2.5 ⁦million investment⁩.

⁦DECISION RISKS⁩

⁦Constraints⁩, ⁦risk⁩ &⁦amp⁩; ⁦compliance⁩

⁦Operational constraints⁩

⁦Unit-level availability is not fully disclosed⁩. ⁦Global Energy Monitor notes that some units may not be operating⁩, ⁦without identifying the units or reasons⁩.

⁦Key risks and compliance considerations⁩

⁦Operational availability at unit level requires verification⁩. ⁦Fuel supply and grid-dispatch conditions were not established in the evidence reviewed⁩.

⁦Related context⁩

⁦Connected Intelligence⁩

⁦Relevant geography⁩, ⁦industry⁩, ⁦market and execution context for this profile⁩.

⁦Common questions⁩

⁦Frequently asked questions⁩

⁦Direct answers to the questions most likely to arise when reviewing this profile⁩.

⁦Where is Parand Power Plant located⁩?

⁦Parand Power Plant is located in Parand⁩, ⁦Tehran Province⁩, ⁦Iran⁩.

⁦Who operates Parand Power Plant⁩?

⁦MAPNA Group operates the plant⁩, ⁦according to MAPNA Group and MAPNA Power Services information⁩.

⁦What is the reported capacity of Parand Power Plant⁩?

⁦MAPNA reported approximately 1⁩,580 ⁦MW of combined-cycle capacity in 2023⁩. ⁦Global Energy Monitor reported 1⁩,578 ⁦MW for the same year⁩.

⁦How is water supplied to the plant’s steam units⁩?

⁦MAPNA reports that the steam units use treated wastewater from Parand city⁩.